Gallery
First photos of £32m Kings Dyke crossing that opens on Monday
Kings Dyke crossing opens on Monday - 50 years after campaign began, Whittlesey, Peterborough Saturday 09 July 2022. Picture by Terry Harris. - Credit: Terry Harris
The £32m Kings Dyke crossing at Whittlesey opens on Monday – six months ahead of schedule.
Work began two years ago this month and the pace of delivery has delighted Cambridgeshire County Council.
It will be known as the Ralph Butcher Causeway after the local councillor for fought for it for 50 years.
Most recent progress to begin constructing a new crossing began in 2014 with a public consultation which found 95 per cent respondents in support.
Jones Bros of Wales won the contract which includes constructing a new road and bridge over the Ely to Peterborough railway line.
You can see the speed of progress from their schedule produced following being awarded the contract.
Programme of Works
Most Read
- 1 Police called to reports of violence in Huntingdon
- 2 Planning proposal for a new café to be reviewed by St Neots Town Council
- 3 Biggest 'shooting star' meteor shower to peak this week
- 4 Police officer speaks out after violent assault left bleed on brain
- 5 Concerns about late-night noise if club is granted alcohol extension
- 6 Ramsey students crowned winners in science competition
- 7 Home of the Week
- 8 Eynesbury Rovers U8s enjoy 'one of greatest seasons in Hunts history'
- 9 Family pay tribute to 'hard worker' father killed in A14 crash
- 10 No water relief for depleted rivers and reservoirs with another heatwave forecast
July 2020 Earthworks start
August 2020 Main site compound built
October/November 2020 Foundations for two key structures (underpass and the bridge) commence
February 2021 underpass scheduled for completion
July 2021 railway bridge scheduled for completion
March 2021 to December 2022 phase 2 and 3 earthworks as well as highway construction works
Jones Bros won the contract after the county council went back to the market last September after failing to agree a final price with original preferred contractor Kier.
The council said: “As a result of this process the total required budget for the project has now reduced from £41.6m to £32m.”
Jones has been widely praised for their efforts, picking up on the way three awards at the CIPR East Anglia Awards to recognise community involvement in a landmark project