Still no defect work completed on Guided Bus

PUBLISHED: 09:46 18 June 2010 | UPDATED: 09:50 18 June 2010

guided bus

guided bus

Archant

Frustration continues at Shire Hall as not one of the six defects on the Guided Busway has yet been fully completed.

NOT one of the six defects on the Guided Busway has yet been fully completed.

Frustration at Cambridgeshire County Council is increasing with each passing week as the authority looks for its contractor, BMA Nuttall, to finish the work necessary prior to taking control of the northern section of the busway.

CCC has said it will not take responsibility for the busway until all the defects, which include flooding of the cycle paths, standing water in the St Ives Park and Ride site, and water leaking onto steal work supporting the bridge over the River Great Ouse, have been rectified.

It means there is still no new date for the opening of the St Ives to Cambridge stretch of the project. The busway is now well over a year behind schedule and millions of pounds over budget.

CCC has said that the project and the contract will be reviewed when the scheme in finally completed - the council had been under pressure to hold a inquiry into the busway project.

Its stance has received support from Department for Transport officials for a Busway review.

Senior councillors expect one of the council’s cross party scrutiny committees to carry out a review of the Busway project once completed.

A public report is also expected to be presented to the council’s cabinet.

Part of the review will assess how the standard civil engineering contract the council has with BAM Nuttall for the project has worked.

Councillors and transport bosses in charge of the project have agreed to share the results of the review with the DfT to help the Government conduct any policy review it may choose.

Roy Pegram, the county council’s cabinet member for growth, infrastructure and strategic planning, said: “It is a good project management discipline to have a review once any major project has been completed to learn lessons for future schemes. The Busway will be no different.

“Our primary concern at the moment is to make sure BAM Nuttall complete the route to the high standards set in the contract.

“Part of our review will fully explore why the contractor has not completed the route on time.”

0 comments

More news stories

Fri, 16:00

A group of St Neots parents whose children have been denied places at the Round House School on Love’s Farm are campaigning to secure entry in time for the September intake.

Fri, 13:26

Dozens of homes and businesses in St Neots are now without electricity as engineers work to use restore power.

Fri, 10:02

Competition is set to be fierce at Ramsey Cricket Club this summer as the players aim to raise money for charity using their batting skills.

Fri, 08:00

A 26-year-old who killed a man has been sent back to prison to complete his sentence after being caught driving while disqualified.

Most read stories

Most commented stories

Local business directory

Cambridgeshire's trusted business finder
HOT JOBS

Show Job Lists

Digital Edition

Image
Read the Hunts Post e-edition E-edition

Newsletter Sign Up

Sign up to receive our regular email newsletter